WELCOME TO
HEDAYA ISLAMIC AND COMMUNITY CENTER

A JOINT PROJECT BETWEEN ISLAMIC CENTER OF KANSAS AND MAS-KANSAS CITY

GALLERY

Thank you for being part of this great community investment for our current and future generation, your unwavering support has made a great impact on the progress of the Hedaya project.

Urgent needs: Youth and children need us more than ever to help them secure a better-protected future.

Solution: Hedaya project is the answer to fulfill various communities needs especially school age children, youth and adults.

Project composition: Hedaya Phase 1 consists of a School, School Gym, and a Community Center which includes a masjid.

What is accomplished: At his point, all buildings are in Phase 1;
all plans, engineering work, permits and related logistics and city requirement are completed, successfully completed significant tasks from drilling piers, moving and filling land, underground utility, and constructing foundations both at ground level and below.
The project is ready to complete as soon as possible, the only obstacle that may slow down the project’s completion is funding.

Construction Update

Project Financials:

$2,230,000 (Paid) School Shelter & GYM (significant tasks from drilling piers, moving and filling land, underground utility, and constructing foundations both at ground level and below.) (11,065 sqft)

  • $4-6M (Estimated Cost) Community Center Construction. (15,798 sqft)
  • $110,000 Available funds (in Trust & receivables).
  • $1,000,000 goal to raise before the end of this year.

What Can We Do?

Make Duaa for the project

اللَّهمَّ لا سَهلَإلَّا ما جَعَلتَه سَهلًا، وأنتَ تَجعَلُ الحَزْنَ إذا شِئتَ سَهلًا
“Allahumma La sahla illa ma ja’altahu sahla wa anta taj’alu al-hazana idha shi’ta sahla”
“Oh allah, nothing is easy except what You have made easy. If You Wish, You can make th edifficult easy.”

Donate, and encourage others to donate

Help us collect funds with Allah’s help

Project Updates

Construction Update Sept 2024

Alhumdolillah we are excited to share that the construction of the School Gym above ground started September 16th 2024. This includes all the wall panels and roof for the Gym inshaAllah. Stay tuned by visiting the gallery to see pictures and videos and our social media channels inshaAllah      

Construction Update Summer 2024

Project Progress / timeline: Completed: The start of the construction with city approved earthwork permit Ground-breaking ceremony Ground preparation– earthwork started Final 3D project building plan published The City of Overland Park came back and demanded a storm shelter (usually waved for non-profits) Structural engineering started extensive and expedited accommodate for construction adjustment After all requested adjustment was met the City of OP Granted final construction permit A construction contract signed with general contractor “Olympus Construction” School Shelter and School GYM building; successfully completed significant tasks from drilling piers, moving and filling land, underground utility, and constructing foundations both at ground

Construction Update Ramadan 2024

Project Progress / timeline: Completed: The start of the construction with city approved earthwork permit Ground-breaking ceremony Ground preparation– earthwork started Final 3D project building plan published The City of Overland Park came back and demanded a storm shelter (usually waved for non-profits) Structural engineering started extensive and expedited accommodate for construction adjustment After all requested adjustment was met the City of OP Granted final construction permit A construction contract signed with general contractor “Olympus Construction” School GYM building wall panels and roof materials ordered. Underway: School GYM foundation, piers, concrete floor School GYM walls and roof Ordered last December